Industrial Renovation – A bay in the middle of the existing pre-engineered metal building was demolished and a taller bay was constructed to allow for a new 40 ton bridge crane. The new bay is 17 feet higher than the existing roof and houses three of the country’s largest injection molding machines. We also designed the mat foundations for the injection molding machines as well as three 60 foot tall silos and a cooling tower.

 